Nuclear Power Equipment Manufacturing Project Agreement Signed On December 20, China Nuclear Industry No. 2 Construction Company and Haiyang Municipal People's Government signed a nuclear power equipment manufacturing project agreement at Fangyuan Hotel in Haiyang City.
2007
On April 21, the first equipment contract of the company's engineering project was signed.
April 17th, AP1000 steel safety shell cooperation memorandum signed
On April 26, Shandong Nuclear Power Equipment Manufacturing Co., Ltd. was established.
On May 14, the company's preparatory staff stationed
On June 20, the first shareholders meeting of the company, one meeting of the first board of directors, and one meeting of the board of supervisors of the first session were held.
On July 3, Shandong Nuclear Power Equipment Manufacturing Co., Ltd. was unveiled.
On November 16th, the AP1000 nuclear power plant CV steel shell head pressing process test achieved the expected results
2008
On February 4 (the 28th day of the lunar month), the chairman of the national nuclear power Wang Binghua visited the company for condolences and investigations.
On March 12, Vice Governor Wang Junmin went to the company construction site for investigation and guidance work.
May 16th, the company's shareholding structure business scope changes adjustment
On May 30, the company's module factory was completed and put into production.
On June 12, Sun Qin, deputy director of the National Energy Administration, visited the company.
On July 6, Wang Renyuan, executive deputy governor of Shandong Province, visited the company.
On August 26, the company officially entered the new office area.
On August 28, Shandong Nuclear Power Equipment Manufacturing Project passed the acceptance test.
On September 1, the feasibility study report of AP1000 steel containment container manufacturing technology research project passed the review
On October 31, the company launched three generations of nuclear power module manufacturing.
On November 5, Li Ganjie, Vice Minister of the Ministry of Environmental Protection visited the company.
On November 13, the third-generation nuclear power domestic module and steel containment purchase contract were signed.
On December 4th, the company's first batch of module products were shipped.
2009
On January 26, Chairman Wang Binghua visited the company on the New Year's Day.
On March 17, the central media focused on three generations of nuclear power equipment manufacturing to the company for interview.
On March 20th, the sixth meeting of the company's shareholders' meeting and the sixth meeting of the first board of directors were held.
On April 17, Director Liu Hua of the National Nuclear Safety Administration and his party visited the company for research and guidance.
On the evening of May 6, the third generation of nuclear power relied on the first steel plate of the steel safety shell bottom cover.
On June 2, the first three-generation nuclear power specialized chemical plant in China won the US ASME nuclear certificate.
On June 18th, the first set of steel safety shell bottom seal factory of AP1000 nuclear power was completed.
At 13:08 on June 29, the largest structural module of the nuclear island of Sanmen Nuclear Power Unit 1 was successfully hoisted in place.
On July 15th, the assembly work of the CV bottom head of the No.1 nuclear power unit was completed.
On the morning of July 23, the on-site assembly work of the CA20 module of the third-generation nuclear power Haiyang nuclear power plant was started.
On September 3, the company successfully passed the on-site NA, NPT, NS certification review of the American ASME Association.
On October 13, Sanmen Nuclear Power Unit No. 1 steel containment shell No. 1 ring steel plate was completed.
On October 31, the CA01 module of Sanmen Nuclear Power Unit No. 1 was completed and manufactured.
At the end of October, the company was listed as a Class A supplier of nuclear power recovery equipment procurement in the United States.
On the afternoon of November 3, the company held the first delegation meeting to elect the first session of the Youth League Committee.
At 15:28 on December 21, the world's first three-generation nuclear power steel safety shell bottom cover was successfully hoisted in place.
2010
On January 15, the seventh meeting of the board of directors of the company's shareholders meeting was held.
On January 23, the company's trade union inauguration meeting and the first member representative conference were held.
On the morning of January 30, the largest structural module of the nuclear island of Haiyang Nuclear Power Unit 1 was successfully hoisted in place.
From February 1st to 2nd, the third-generation nuclear power equipment manufacturing project passed the National Energy Administration.
On February 21, the company won the Yantai City Emerging Industry Development Award.
On April 9, the company signed the AP1000 steel containment procurement contract for his Taohuajiang nuclear power project.
On May 19, the former chairman of the Westinghouse Company of the United States led a delegation to visit
At 11:18 am on June 13, the CV bottom head of Sanmen Nuclear Power Unit 2 was successfully hoisted in place.
On June 18, Zhang Fubao was appointed as the chairman of the second board of directors of the company.
In July, the company developed a patent for a utility model for “a type of head-finishing mold”
On September 7, the company's new leadership team was established.
At 13:30 on September 27, the largest structural module CA01 of Haiyang Nuclear Power Unit 1 was hoisted in place.
In October, the company's CV workshop won the title of the central enterprise red flag team
In October, the company's "super large head plate integral press forming process and safety shell head" won the national invention patent
On October 18th, the company's technology center was identified as a provincial technology center.
At 11:35 am on October 22, the former Political Bureau of the CPC Central Committee and Vice Premier of the State Council Zeng Peiyan came to inspect and guide the work.
At 9:07 on October 30, the CV bottom head of Haiyang Nuclear Power Unit 2 was hoisted in place.
On November 13th, the US public television network went to the national nuclear equipment to shoot a feature documentary.
On December 2, the first inland AP1000 nuclear power module factory in China was unveiled.
On December 8, the Czech government’s nuclear power plant expanded government commissioners to visit and exchange
On December 10, the company passed the civil nuclear safety equipment manufacturing license expansion examination
In December, the company won the first prize of Shandong Enterprise Management Modernization Innovation Achievements.
On December 22, the company was awarded the three-standard integrated management system certification.
2011
At 14:16 on February 22, the CA03 module of Sanmen Nuclear Power Unit 1 was successfully hoisted in place.
On the afternoon of March 4, the National Nuclear Power and the Shandong Provincial Government signed a strategic cooperation framework agreement.
At 14:56 on March 13, Haiyang Nuclear Power Unit 2 CV cylinder 1 ring hoisted in place
On March 18, Zhang Guobao, deputy director of the Economic Committee of the National Committee of the Chinese People's Political Consultative Conference, former deputy director of the National Development and Reform Commission, and former director of the National Energy Administration visited the company.
On March 1, the company has nuclear-grade equipment modules and pipeline prefabrication qualifications.
On March 28, the company’s first party member congress was successfully held.
In April, the company has two inventions that have obtained national patents.
In April, the company was selected as one of the first batch of “four hundred” projects in Shandong Province.
Recently, the company's project was selected for major science and technology projects in Shandong Province.
At 10:50 on June 11th, the assembly work of the CV top seal head of the No.1 nuclear power unit was started.
On June 25, CV head manufacturing technology passed the identification of scientific and technological achievements of the Nuclear Energy Industry Association.
On July 18, the company was approved to carry out IHP manufacturing and assembly activities.
On July 21, the first domestic AP1000 integrated top cover assembly was started.
At 16:55 on July 21, the world's first AP1000 nuclear power unit steel containment was completed.
On September 11, the IHP site assembly work of the No.1 nuclear power unit was officially launched.
On September 29, the company won another utility model patent.
On October 27th, the main equipment of the AP1000 nuclear power IHP localization project was fully adjusted and completed.
In October 2011, the company was awarded the title of “Enterprise Team Safety Construction Demonstration Enterprise” in Yantai City.
In November, the company's five technologies were awarded national patent certificates.
On the morning of December 13, Wei Lock unveiled the National Nuclear Equipment Branch of the National Nuclear University.
In December, the company became a provincial high-tech enterprise through the identification of high-tech enterprises.
On December 29, the project site of Hubei Xinneng Nuclear Power Equipment Co., Ltd. was successfully auctioned.
2012
In February, the company was awarded a pressure vessel manufacturing license
On March 24th, the CAP1400 containment water distribution test project was successfully completed and handed over.
On March 31, the company won the title of “2011 Top 100 Taxpayers in the City” of Yantai City.
On April 12, the CAP1400 water distribution test facility for the major special project of pressurized water reactor was launched.
On April 12, the company successfully passed the ASME extended certificate joint inspection
In April 2012, the company was approved as a member of the Shandong Special Equipment Association.
On April 24, the company's physical and chemical laboratory passed the first-level qualification review.
At 15 o'clock on April 27, the third-generation nuclear power autonomy relied on the completion of the project steel main containment body.
On the afternoon of June 16, Ma Kai, former State Councilor and Secretary of the State Council, came to guide the work.
On June 16, the AP1000 and follow-up projects signed a strategic cooperation framework agreement on equipment procurement.
On August 24th, Haiyang Nuclear Power Unit IHP upper middle shield cover assembly was in place.
On September 20th, the third-generation nuclear power AP/CAP equipment and materials supplier meeting was held
On November 24th, the company was awarded the title of outstanding enterprise in the national power industry.
On November 30, the company became the first first-class safety production standardization enterprise in the nuclear power industry.
On December 6, the company's integrated roof assembly localization project passed the project completion acceptance
On December 19th, the company passed the annual review of the “three-standard” system.
From December 21st to 22nd, AP1000 steel containment national major special project passed pre-acceptance
2013
From January 14th to 15th, the company passed the "U" & "U2" certification review of the American ASME Association.
On January 18th, all the mechanical modules of the No.1 unit of the project were delivered.
At 19:20 on January 19th, relying on the project, the three-core nuclear power unit 1 nuclear island IHP was successfully put in place.
On January 25, the company was awarded the title of Advanced Unit for National Nuclear Power System Safety Production.
On January 29th, the third generation of nuclear power AP1000 world's first pile of CV top heads in place
On January 29, the second phase of the company passed the acceptance check of the overall project.
In February, the company won two invention patents.
In March, the company's IHP workshop won the title of “Worker Pioneer” of the National Energy Chemistry System.
At 17:01 on March 15th, Haiyang Nuclear Power Unit 1 nuclear island IHP is in place
At 9:36 on March 29, the CV top head of Haiyang Nuclear Power Unit 1 was hoisted in place.
On April 1st, the company released the CAP1400 demonstration project preparation work start order
On April 27, the National Nuclear Power Equipment Manufacturing Business Working Conference was held in Haiyang.
On April 26, the 1000-ton gantry self-closing tensile load test device passed the scientific and technological achievements appraisal
In May, Peng Fei, the employee of the company, was awarded the title of “Central Enterprise Youth Position Expert”.
On May 31, the CV supply contract for the first phase of Xu Dabao Nuclear Power Project was signed.
From July 13th to 14th, the company passed the D-class pressure vessel design (certification) license appraisal review
On the morning of July 16, the production of steel containment for the first phase of the Xu Dabao nuclear power project in Liaoning started.
On July 25, the company convened the party's mass line education practice activities mobilization meeting
On July 25, Liu Hua, chief engineer of nuclear safety of the Ministry of Environmental Protection, went to the company for research work.
On July 25, the contract for the supply of safety products such as the newly-built three-generation nuclear power project was signed.
On August 23, AP1000 nuclear power CV automatic welding process passed expert appraisal
On October 26, South Africa’s Deputy Minister of Energy Barbara Thompson visited the company.
In November, the AP1000 integrated top cover assembly was made in China.
On November 27th, CAP1400 CV manufacturing feasibility study report and budget passed expert review
From November 27th to 29th, the company passed the three-standard integration re-certification and the CNNC supplier evaluation review.
In November, the company obtained another national patent for an invention.
On December 8, the South African Ministry of Energy delegation visited our company again.
On December 31, the company's eight standards passed the measurement and construction assessment
2014
In January, the company won a national power worker technical achievement award.
January 24, CAP1400 nuclear power plant steel containment manufacturing start
On the morning of March 13, the CAP1000 follow-up project mechanical module procurement contract was signed
On March 14, the National Nuclear Power and Haiyang Municipal Government signed a strategic cooperation framework agreement on nuclear power industry development.
In March, the company's nuclear power welding process management system obtained the national computer software copyright.
On April 19, the Deputy Director of the National Nuclear Safety Administration Guo Cheng Station visited the company.
On April 28, Wang Guojun served as general manager of the company.
On April 29, Xu Zhenchao, vice chairman of the All-China Federation of Trade Unions, visited the company's employees before May Day.
On May 15th, the company added two new areas of civil nuclear safety manufacturing licenses.
On June 4th, the company was approved to become a first-class compliance enterprise for safety production standardization.
From June 22nd to 23rd, the national major special AP1000 integrated roof cover manufacturing technology subject passed pre-acceptance
2015
From February 2nd to 13th, the company's welding test center held the first nuclear-level project test.
On March 27th, the 17th meeting of the company's shareholders meeting and the 6th meeting of the third board of directors were held.
On March 29th, Shandong Province’s major special project “large-scale advanced pressurized water reactor steel containment pressure vessel” passed the acceptance test.
At 11:30 on March 31, AP1000 sub-module of AP1000 Haiyang Nuclear Power Unit 3 was successfully hoisted in place.
At 9:30 on April 2, the three-core nuclear power unit 2 IHP upper shield hoisting is in place
On April 11, the company successfully passed the ASME renewal certificate review and increased the NA and NS qualifications.
On April 17, the company organized for the first time to undertake the nuclear safety welder theory test of the National Nuclear Safety Administration.
On April 21, the demonstration project contracting factory SC structure procurement contract was signed.
On May 11, Li Ganjie, Vice Minister of the Ministry of Environmental Protection visited the company.
On May 25, Liu Qi, deputy director of the National Energy Administration, visited the company.
At 14:00 on May 26, the CA20 module 1# assembly of the National Nuclear Water Reactor Model Demonstration Project was successfully flipped.
At 17:25 on June 21, relying on the project, the three-door unit 2 reactor pressure vessel integrated top cover was hoisted in place.
At 14:58 on July 6, Sanmen Nuclear Power Unit 2 safety shell top seal was successfully placed
On August 20, the national nuclear equipment civil nuclear safety equipment manufacturing license continued to be approved
From September 9th to 11th, the review meeting on the manufacturing standards of the national nuclear equipment steel containment and integrated roof components was successfully held.
From November 5th to 6th, the “Nuclear Power Plant Sliding Gate Transmission Mechanism” and the “Integrated Stacking Top Assembly Cantilever Crane” passed the identification of scientific and technological achievements of the Nuclear Energy Industry Association.
On November 24, the groundbreaking ceremony for the CA20 module assembly project of Lufeng Nuclear Power Phase I Project was successfully completed.
From December 16th to 17th, the national nuclear equipment passed the "U" & "U2" accreditation review of the American ASME Association.
At 22:30 on December 4, the air pressure test of the steel containment of Unit 1 of Haiyang Nuclear Power Station was successfully completed.
2016
On January 20, General Manager Meng Zhenping of the National Power Investment Corporation expressed condolences to the nuclear model workers and employees in difficulty.
From January 22nd to 24th, the company successfully completed the D-class pressure vessel manufacturing renewal certificate review.
On March 12th, the three-way replacement of the normal residual heat exhaust system and the passive core cooling system of Sanmen No. 1 unit was successfully completed.
On April 19th, the company's "Civil Nuclear Safety Equipment Welder Welding Operator Assessment Center" was officially unveiled.
On May 11, the first batch of Pakistan Kassem Port coal-fired power station project equipment was successfully delivered.
On June 4, the company won the “2015 Yantai Mayor Quality Award”
From June 27th to 29th, the company obtained the intellectual property management system certification.
At 16:40 on July 5, the world's first CAP1400 nuclear power unit equipment gate function test was a complete success
On July 20th, the world's first CAP1400 nuclear power unit equipment gate was successfully shipped
On August 24th, Lufeng Nuclear Power 1# unit CA01 was officially launched.
On the morning of September 13, the Governor of Shandong Province Guo Shuqing visited the company.
On September 28th, the demonstration project 1# unit CV cylinder two-ring assembly transition work successfully completed
On October 14, the second meeting of the company's trade unions was successfully held.
On December 9th, the company held a leadership team to announce the announcement.
On December 9th, the company achieved good results in the first national civil nuclear safety equipment welder skill competition.
On December 16, won the title of the sixth national advanced equipment management unit in the power industry
2017
On January 18th, the company tenth
2018
In January, the company convened a party member leading cadre democratic life meeting to solicit opinions and suggestions. The symposium was to conscientiously implement the requirements of the national power investment party group and the national nuclear power party group, and fully do a good job in collecting and collecting opinions on the democratic life of party members and leading cadres. On January 23, the company The party committee organized a symposium of representatives of department heads, employee representatives, and party members. The meeting was presided over by Li Kezhong, member of the party committee, secretary of the Disciplinary Committee, and acting chairman.
The major special project "Study on Ultrasonic Testing Technology for Butt Welds of Steel Containment" was successfully held. The company organized a national expert review meeting for the sub-project 4 of the national key science and technology project "CAP1400 steel containment key manufacturing technology". The participating experts carefully reviewed and carefully discussed the content of the project, and fully affirmed the scientific nature of the technical route of the project. At the same time, it put forward related content that needs to be improved, and finally formed an expert review opinion, which was beneficial to protect. The correctness and scientificity of the follow-up research route.
In February, Yu Wenbao, member of the National Nuclear Power Party Group and deputy general manager, visited the victims of the nuclear equipment in the country. On February 6, Yu Wenbao, member of the National Nuclear Power Party Group and deputy general manager, went to Haiyang, Shandong Province to represent the National Nuclear Power Party Group to express condolences to the nuclear-fighting equipment families. Give them the care and warmth of the organization and give them a greeting and a good blessing.
The company held the 2017 Democratic Life Meeting on the morning of February 7. The National Nuclear Equipment Party Committee held the 2017 Party Leaders and Cadres' Democratic Life Meeting. The company's leading team and leading members adhered to the theme of the democratic life meeting and focused on the "six aspects". Adhere to the problem-oriented, contact the individual reality, conduct in-depth party analysis, and earnestly carry out criticism and self-criticism. Yu Wenbao, member of the National Nuclear Power Party Group and deputy general manager, and Jian Jianhua, a full-time organizer of the Provincial Committee of the Provincial Party Committee, and other leading comrades attended the meeting.
The company held the 2018 work conference and the second session of the second employee representative conference. On February 9, the company held the 2018 work conference and the second session of the second job congress, which comprehensively summarized the work in 2017, analyzed the situation in depth, and arranged the deployment of work in 2018. We will mobilize the broad masses of cadres and employees to not forget their original intentions, keep their mission in mind, strengthen their confidence and advance their efforts, and make new and greater contributions to the national power investment and national nuclear power! Wang Guozhen, chairman and party secretary of the company, presided over the meeting and delivered a speech.
The company visited the employees who had difficulties in condolences on February 11th. On the occasion of the coming of the Spring Festival, the party secretary of the company, the chairman of the board of directors Wang Guozhen, the secretary of the Disciplinary Committee, and the acting chairman Li Kezhong visited the company to express condolences to the company's six difficult employees. They sent the organization's care and New Year blessings.
The company won the 3rd China Equipment Management Innovation Achievement Award. The 3rd (2016-2017) China Equipment Management Innovation Achievements Selection Event was announced by the China Equipment Management Association. The company recommended the "Steel Safety Shell Insertion Board". The research and application of the automatic welding equipment for components and through-sleeve sleeves won the award for management innovation.
The company won the title of “Star Enterprise” on February 28th. The company was awarded the title of “Star Enterprise” by the Haiyang Municipal Party Committee and the Municipal Government in the 2015 2017 Target Target Assessment Award and Reimbursement and the 2018 Economic Work Conference held in Haiyang City. Conference commendation.
In March, the company held a symposium on the 2018 United Front Work. On the morning of March 2, the 2018 United Front Work Symposium was held. Party Secretary and Chairman Wang Guozhen attended the forum. A total of 11 employees of the Democratic Party and minority representatives attended the symposium. The meeting was chaired by Li Kezhong, secretary of the Disciplinary Committee and chairman of the trade union. At the meeting, representatives of the democratic parties and ethnic minorities revolved around the reform, development and stability of enterprises, made speeches one by one, made suggestions and suggestions, and put forward pertinent opinions and suggestions on how to do a good job in united front work.
The company held the start-up meeting of Qinghai Hainan 400MW wind power project On March 15th, the company held the kick-off meeting of Qinghai Hainan 400MW wind power project, marking the official entry of the project into the implementation phase, and also another breakthrough in the company's new energy outside the nuclear power sector.
The first meeting of ASME renewal and forensic joint inspection was held. On the morning of March 27th, the first meeting of ASME renewal and forensic joint inspection was held in the company. The meeting was presided over by Yang Zhongwei, the chief engineer of the company. Wang Hongtao, general manager of the company, attended the meeting. This ASME joint inspection involves N, NPT, NS certificate extension, N3 certificate forensics and ASME material supply.
The company successfully passed the ASME renewal certificate review on March 30th. The company successfully passed the inspection and review by the American Society of Mechanical Engineers (ASME) Joint Inspection Unit. It believes that the quality assurance system and operation of the national nuclear equipment meet the requirements of the ASME standard and will be recommended to the ASME Association. , granted nuclear equipment N, NPT (including ASME material supply), NS, N3 qualification certificate. This application for ASME renewal certificate extension is the first time that the company obtained ASME N, NPT, NA, NS certification in 2009, and after successfully renewing certificates in 2012 and 2015, it successfully passed the ASME renewal certificate and certificate review for the third time. .
In April, the company held the 2018 party building and party style and clean government construction and anti-corruption work meeting. On April 2, the company opened the party building in 2018 and the party style and clean government construction and anti-corruption work meeting. The meeting thoroughly studied and understood Xi Jinping's new era of socialism with Chinese characteristics, comprehensively implemented the spirit of the group company and the national nuclear power party building and party style and clean government construction and anti-corruption work conference, summed up the company's 2017 party building, party style and clean government building and anti-corruption work, deployment In 2018, party building, party style and clean government building and anti-corruption work will further mobilize the cadres and staff to not forget their original intentions, keep their mission in mind, strengthen their confidence and adapt themselves, and strive to achieve the new goal of "innovation and efficiency, high-quality development", to ensure full completion. Years of work tasks are escorted.
The demonstration site successfully completed the “SC four-in-one module” transshipment work. On April 21, the demonstration site completed the first “SC four-in-one module” transshipment work. “SC Four-in-One” is the first SC product to be assembled in the demonstration project. The entire transshipment work lasted 8 hours.
The air deflector project won the 2017 China Nuclear Energy Industry Association Science and Technology Award. On April 23, the China Nuclear Energy Industry Association held the Sustainability Forum and the 2017 Nuclear Energy Technology Awards Ceremony in Beijing. The AP/CAP series independently developed by the company. The nuclear air power plant passive air deflector manufacturing technology won the third prize of the China Nuclear Energy Industry Association Science and Technology Award.
In May, Zhang Tao, deputy director of the Weihai Municipal Development and Reform Commission, visited the company. On the afternoon of May 15, Zhang Tao, member of the party group and deputy director of the Weihai Municipal Development and Reform Commission, went to the company to conduct work research. The chairman of the company, party secretary Wang Guojun, deputy general manager Chen Zhanghua, Hu Guangze and so on received the guests and his party.
The company's first self-manufactured AP1000 nuclear power unit personnel gate through-component manufacturing completed the factory on May 17th. The lower personnel gate penetration assembly of Xu Dabao Unit 1 independently developed by our company was successfully manufactured and shipped on May 18, 2018. This is the first AP1000 nuclear power unit personnel gate penetration component manufactured by our company.
In June, the company held the second quarter of 2018 safety production committee and safety production month activities kick-off meeting on June 4, held the second quarter safety production committee and safety production month activities kick-off meeting
The company won the winners of the 2016-2017 National "Ankang Cup" competition. Recently, the All-China Federation of Trade Unions and the Emergency Management Department jointly issued a batch of winning groups and winners in the 2016-2017 National "Ankang Cup" competition. The team and outstanding individuals were commended, and the company won the winner of the 2016-2017 National “Ankang Cup” competition.
Westinghouse Senior Representative and Delegation Visited the Company to Exchange International Project Cooperation On June 13, William Poirier, Vice President of Nuclear Power Plant Business of AP1000 China Project of Westinghouse Industrial Products International visited the company and exchanged and discussed matters related to international nuclear power project cooperation. Chairman of the company Wang Guojun, General Manager Wang Hongtao, and Deputy General Manager Song Fengbo received the guests and their party.
Wang Fengxue, general manager of the national nuclear power research company On June 22, Wang Fengxue, general manager of the national nuclear power research company. Hao Hongsheng, assistant general manager of the national nuclear power and general manager of the Ministry of Human Resources, Liu Junxi, director of the General Office, and Gao Qing, director of the party group, accompanied the investigation.
Qian Zhimin, Chairman of the Board of Directors and Party Secretary of the State Power Investment Group Co., Ltd. On the afternoon of June 27, Qian Zhimin, the chairman and party secretary of the State Power Investment Group Co., Ltd., researched the company. In the course of on-site investigation, Chairman Qian was very concerned and inquired in detail about the specific problems of the national nuclear equipment operating efficiency, the inspection capacity of external units, and the automatic welding qualification rate. After listening to the report on the preparation of nuclear power plants for nuclear power plants, Chairman Qian pointed out that the construction of equipment related to offshore wind power is the strength of national nuclear equipment. The national nuclear power and related departments of the group companies are required to support the national nuclear equipment to participate in offshore wind power equipment. Manufacturing, giving full play to the advantages and strengths of the company and enhancing the core competitiveness of the national nuclear equipment.
The company and Westinghouse cooperated on the international project to carry out the second round of negotiations. On June 28th, David Durham, senior vice president of the global nuclear power business of Westinghouse Electric Company, visited the nuclear equipment of the United States to conduct a second round of negotiations on international project cooperation. Chairman Wang Guojun, General Manager Wang Hongtao and Deputy General Manager Song Fengbo attended the meeting.
The company passed the annual intellectual property management system certification review On June 28, the company passed the annual review of Zhongzhi (Beijing) Certification Co., Ltd., and the operation of the company's intellectual property management system meets relevant national requirements.
On the eve of the July 1st, the party committee of the company sympathized with the difficult party members. On the 28th of the founding of the party, on the occasion of the 97th anniversary of the founding of the party, the party secretary of the nuclear equipment, the chairman of the board of directors Wang Guozhen, the secretary of the Disciplinary Committee and the chairman of the labor union Li Kezhong, on behalf of the company party committee, consoled the difficult party members.
In July, the company held a summary and commendation meeting to mark the 97th anniversary of the founding of the party. On July 3, the company solemnly held a summary and commendation meeting to celebrate the 97th anniversary of the founding of the party. The main task is to celebrate the party’s 97th birthday, relive the party’s glorious history, relive the party’s pledge, commend new individuals, and inspire all cadres and staff to not forget their original intentions and keep their mission in mind, contributing to the company’s “innovation, efficiency and quality development”. Wisdom and strength. The meeting was presided over by Li Kezhong, member of the party committee, secretary of the Disciplinary Committee, and chairman of the labor union.
The company held a "new mission, a new journey" to celebrate the 97th anniversary of the founding of the party and the 11th anniversary of the company's establishment. In order to commemorate the 97th anniversary of the founding of the Communist Party of China and celebrate the 11th anniversary of the company's founding, on July 3, the company organized a "new mission, a new journey" "Step by step activities, more than 600 employees from 16 departments of the company participated. The ceremony was hosted by Li Kezhong, secretary of the Disciplinary Committee and chairman of the labor union.
The company was selected as the first “Top 100 High-tech Enterprises” in Shandong. On July 9, the list of top 100 enterprises in Shandong Province's high-tech enterprise innovation capability (abbreviation: Top 100 High-tech Enterprises) was first released, and the company was selected as the first “Top 100 High-tech Enterprises” in Shandong.
Liu Jianxing, deputy director of the International Cooperation Center of the National Development and Reform Commission, researched the company. On July 11, Liu Jianxing, deputy director of the International Cooperation Center of the National Development and Reform Commission, and his party visited the company. Song Zhifang, deputy mayor of Haiyang Municipal Government, and Wang Hongtao, general manager of the company, received the guests and his party.
Xie Jun, a member of the National Power Investment Party Group and the head of the Discipline Inspection Team, researched the company on July 12. On the 12th of July, Xie Jun, a member of the National Power Investment Party Group and the head of the discipline inspection team, and a six-person research company. Jiang Kai, deputy head of the State Electricity Inspection and Discipline Inspection Team, director of the Discipline Inspection and Supervision Department, Wu Fang, deputy general manager of the National Nuclear Power, and the responsible comrades of the State Power Investment Inspection Office and the State Nuclear Power Discipline Inspection and Supervision Department accompanied the company's leadership team to accompany the investigation.
The soft topic of “Principal Delivery Feasibility Study of Large Modules of Non-Energy Nuclear Power Plants at Binhai Site” passed the national nuclear power inspection and acceptance. On July 12th, the company’s soft project on the feasibility of the overall delivery of large modules of non-activated nuclear power plants in coastal sites passed the national nuclear power experts. Group acceptance.
Jiang Yi, a director of the State Power Investment Corporation and deputy secretary of the party group, on July 24, Jiang Yi, a director of the State Power Investment Corporation and deputy secretary of the party group. Yu Wenbao, member of the National Nuclear Power Party Group and deputy general manager, Xia Zhongshu, secretary of the National Electricity Investment Committee, accompanied by the State Power Investment Office and the company's leadership team.
The company convened the party committee to implement the spirit of the party group (expansion) meeting of the group company in 2018. On July 30, the company organized the 19th party committee (expansion) meeting of the company in 2018 and implemented the spirit of the party group (expansion) meeting of the group company in 2018 . The meeting was presided over by Party Secretary and Chairman Wang Guozhen.
In August, the company's “Inspector Evaluation and Management Standards for Welder Workload Points” management innovation achievements won the third prize of the group company. From July 12th to 13th, the group company management innovation results review meeting was held in the talent college, the company production department welder management The management innovation topic of the room evaluation “Assessor Evaluation and Management Standard for Welder Workload Points System” won the third prize of the management innovation achievement of the group company.
The company's trade union held the first "Golden Autumn Aid" activity On August 23, the company's trade union held the first "Golden Autumn Aid" symposium, and the children of the employees and the parents of the employees attended the symposium. Li Kezhong, secretary of the company’s disciplinary committee and chairman of the labor union, attended the event.
The company carried out the “five small innovation achievements creation action” In order to thoroughly implement the group company's innovation and development concept, on August 30-31, the National Nuclear Equipment Organization held the 2018 “Five Small Innovation Achievements Creation Action” results performance review meeting, company leader Wang Hongtao , Tang Chuanle, Hu Guangze, Li Kezhong, Yang Zhongwei, and representatives of eight judges and 54 achievements attended the review meeting. In this activity, a total of 1 first prize, 3 second prizes, 8 third prizes, 18 merit awards and 24 encouragement prizes were judged. At the same time, there were 12 first, second and third prizes for the judging. The results are recommended to participate in the first group company innovation competition organized by the group company working committee.
The company held a retreat. On August 14, the company held a retreat. The meeting fully conveyed and implemented the spirit of the Group's 2018 Party Group (Enlarged) Conference, and thoroughly studied the new era development strategy of the group company that Chairman Qian Zhimin informed at the meeting, and carefully grasped the group company to build a globally competitive international first-class energy enterprise. The overall strategic objectives and innovative, coordinated, green, open, shared development concepts and strategic positioning of energy technology developers, clean low-carbon energy suppliers, energy ecosystem integrators, step-by-step strategic objectives and industrial development initiatives. The meeting was presided over by Wang Hongtao, general manager and deputy secretary of the party committee.
Guo Hongbo, Secretary of the State Power Investment Corporation and Secretary of the National Nuclear Power Party, went to the company to carry out special investigations on party group and patrol rectification work. On August 21, Guo Hongbo, the national power investment assistant and secretary of the National Nuclear Power Party Group, went to the national nuclear equipment to carry out the work of party group and patrol rectification work. Investigate the National Nuclear Power Engineering Management Department, the main party and party secretary of the company, and the secretary of the Disciplinary Committee to participate in the survey and discussion.
The first set of basic ring shipments of Qinghai Hainan 400MW wind power project undertaken by the company was delivered at 00:15 on August 24, 2018. The first set of basic ring of Qinghai Hainan 400MW wind power project was successfully delivered. It marks that the company has made new breakthroughs in new energy projects, and also verified the company's product manufacturing capabilities, providing a basis for further expansion of the new energy market.
In September, the company successfully held the 2018 vocational skill competition in Haiyang City. The company went smoothly on September 9.